dbo:abstract |
The Balloki Power Plant is a 1,223 MW natural gas power plant completed in mid 2018 in Pattoki, in the Punjab province of Pakistan. Groundbreaking was commenced on November 11, 2015, and construction was scheduled for completion by December 2017. The project utilizes regasified liquefied natural gas (RLNG) for fuel, with diesel as an alternate backup. A 40 kilometer long transmission line with a capacity of 500 kilovolts was also constructed between the new plant and a grid station in southern Lahore. Bidding was open to international firms for the 82 billion rupee project. China's Harbin Electric Company was announced as the lowest evaluated bidder for the project on October 2, 2015, having offered a levellised electricity cost of 7.973 cents per unit, outbidding the Turkish conglomerate Enka İnşaat ve Sanayi A.Ş. and GE Consortium which both stood in second with 8.185 cents per unit tariff, followed by China Machinery Eng Co (CMEC) & SEFC at 8.304 cents, and Hyundai Engineering at 8.332 cents per unit. (en) |
dbo:buildingStartDate |
November 2015 |
dbo:buildingStartYear |
2015-01-01 (xsd:gYear) |
dbo:country |
dbr:Pakistan |
dbo:installedCapacity |
1223000000.000000 (xsd:double) |
dbo:location |
dbr:Punjab,_Pakistan dbr:Chunian dbr:Balloki |
dbo:openingYear |
2018-01-01 (xsd:gYear) |
dbo:owner |
dbr:Harbin_Electric dbr:NPPMCL |
dbo:status |
Completed |
dbo:wikiPageExternalLink |
https://www.nppmcl.com/project/balloki-power-plant/%7Cnppmcl.com |
dbo:wikiPageID |
48558339 (xsd:integer) |
dbo:wikiPageLength |
6181 (xsd:nonNegativeInteger) |
dbo:wikiPageRevisionID |
1076130487 (xsd:integer) |
dbo:wikiPageWikiLink |
dbr:Punjab,_Pakistan dbr:List_of_barrages_and_headworks_in_Pakistan dbr:List_of_power_stations_in_Pakistan dbr:Pattoki dbr:Megawatt dbr:Chunian dbr:Enka_İnşaat_ve_Sanayi_A.Ş. dbr:GE dbr:Liquefied_natural_gas dbc:2015_establishments_in_Pakistan dbr:Exim_Bank_of_China dbc:Energy_in_Punjab,_Pakistan dbc:Natural_gas-fired_power_stations_in_Pakistan dbr:Pakistan dbr:Harbin_Electric dbr:Head_Balloki dbr:Lahore dbr:Punjab_(Pakistan) dbr:World_Bank dbr:Balloki dbr:NPPMCL dbr:Hyundai_Engineering |
dbp:commissioned |
2018 (xsd:integer) |
dbp:constructionBegan |
November 2015 (en) |
dbp:cost |
$ million (en) |
dbp:country |
dbr:Pakistan |
dbp:location |
dbr:Punjab,_Pakistan dbr:Chunian dbr:Balloki |
dbp:name |
Balloki Power Plant (en) |
dbp:nameOfficial |
Balloki Power Plant (en) |
dbp:owner |
dbr:NPPMCL (en) |
dbp:psElectricalCapacity |
1223.0 |
dbp:status |
Completed (en) |
dbp:thFuelPrimary |
dbr:Liquefied_natural_gas |
dbp:website |
https://www.nppmcl.com/project/balloki-power-plant/%7Cnppmcl.com |
dbp:wikiPageUsesTemplate |
dbt:Coord dbt:Portal dbt:Reflist dbt:To_USD dbt:Infobox_power_station |
dcterms:subject |
dbc:2015_establishments_in_Pakistan dbc:Energy_in_Punjab,_Pakistan dbc:Natural_gas-fired_power_stations_in_Pakistan |
georss:point |
31.1887 73.8895 |
rdf:type |
owl:Thing dbo:Infrastructure wikidata:Q159719 geo:SpatialThing dbo:ArchitecturalStructure dbo:PowerStation |
rdfs:comment |
The Balloki Power Plant is a 1,223 MW natural gas power plant completed in mid 2018 in Pattoki, in the Punjab province of Pakistan. Groundbreaking was commenced on November 11, 2015, and construction was scheduled for completion by December 2017. The project utilizes regasified liquefied natural gas (RLNG) for fuel, with diesel as an alternate backup. A 40 kilometer long transmission line with a capacity of 500 kilovolts was also constructed between the new plant and a grid station in southern Lahore. (en) |
rdfs:label |
Balloki Power Plant (en) |
owl:sameAs |
yago-res:Balloki Power Plant wikidata:Balloki Power Plant dbpedia-no:Balloki Power Plant http://ur.dbpedia.org/resource/بلوکی_پاور_پلانٹ https://global.dbpedia.org/id/F5n5 |
geo:geometry |
POINT(73.889503479004 31.18869972229) |
geo:lat |
31.188700 (xsd:float) |
geo:long |
73.889503 (xsd:float) |
prov:wasDerivedFrom |
wikipedia-en:Balloki_Power_Plant?oldid=1076130487&ns=0 |
foaf:homepage |
https://www.nppmcl.com/project/balloki-power-plant/%7Cnppmcl.com |
foaf:isPrimaryTopicOf |
wikipedia-en:Balloki_Power_Plant |
foaf:name |
Balloki Power Plant (en) |
is dbo:wikiPageWikiLink of |
dbr:Punjab_Thermal_Power_Plant dbr:Privatisation_in_Pakistan dbr:Bhikki_Power_Plant dbr:List_of_power_stations_in_Pakistan dbr:Chief_Ministership_of_Shehbaz_Sharif dbr:China–Pakistan_Economic_Corridor dbr:Kasur_District |
is foaf:primaryTopic of |
wikipedia-en:Balloki_Power_Plant |