PROGRESS OF NEW BRIDGE AT BRIDGEWATER - The Mercury (Hobart, Tas. : 1860 - 1954) - 14 Mar 1939 (original) (raw)
Loading article contents, please wait...
Tue 14 Mar 1939 - The Mercury (Hobart, Tas. : 1860 - 1954)
Page 7 - PROGRESS OF NEW BRIDGE AT BRIDGEWATER
PROGRESS OF NEW BRIDGE AT BRIDGEWATER
SECTIONS of the new bridge un der construction over the River Derwent at Bridgewater. The existing wooden bridge is shown in the background. Help
SECTIONS of the new bridge under construction over the River Derwent at Bridgewater. The existing
wooden bridge is shown in the background.
Having completed the difficult pre-
liminary work, steady progress is being
made with the erection of a new bridge
over the River Derwent at Bridgewater.
The new bridge will carry rail, road, and
foot traffic, and special preparations
are being made for a wide opening span
on the main river channel to permit of
the passage of sea-going vessels.
About 50 men are employed on the
bridge work. The chief work has been
done on the concrete piers, commencing
from the Granton side of the river.
There are eight sets of piers, and at
each set 20 special piles have been
driven. Each wooden pile has been
fitted with a concrete sleeve from a
point where it enters the mud on the
river bottom, and the Junction with the
concrete pier. It is the first time
composite wood and concrete piles
have been used for bridge construc-
tion in Tnsmania, and the experiment
promises to be highly successful in pre-
serving the wood, which, without the
concrete sleeve, would be exposed to
the action of the water and borer pests
above the point where the piles enter
From the Granton end a start has
been made with the application of the
concrete road deck. Steel girders have
been placed in position for seven spans
of the bridge, and in a short time it
is expected that the concrete decking
will be extended almost half way across
the river. Because of the bad condi-
tion of the existing wooden bridge, the
work on the new bridge is being expe-
dited, and although provision hass been
made for the railway line on the up-
stream side of the new traffic bridge,
the work of laying the rails probably
will not be done until the road bridge ls
well on the way towards completion.
Provision is being made on the road
bridge for a section for pedestrians, and
there will be nearly 30 feet of roadway
on the bridge for vehicular traffic.
The most difficult part or the work
above the water level will be on the
section to provide an opening for steam-
ers on the main river channel. A huge
tower will he erected on each side of the
opening span, and the bridge sections
will be raised high into the air to pro-
vide the necessary opening. The pro-
vision of concrete cylinders in the deep
part of the stream as a foundation for
each corner of the opening span has
presented a difficult task. The cylin-
ders have been got down to an average
depth of about 86ft., and it is expected
that the work on them will be completed
shortly. A huge steel crane hns been
built on the Bridgewater side of the
river to convey girders from the rail-
way siding to the deep water, and this
arrangement of handling the heavy
steelwork is proving satisfactory.
At one stage, when all the work was
being done below the water level, it ap-
peared that the Derwent bridge at Ho-
bart would he completed before the
Bridgewater structure, but if the pre-
sent rate of progress is maintained it
is likely that the Bridgewater bridge
will be the first of the two structures in