DELAYS IN WORK - Construction Of Bridges - The Mercury (Hobart, Tas. : 1860 - 1954) - 3 Jul 1942 (original) (raw)
Loading article contents, please wait...
Fri 3 Jul 1942 - The Mercury (Hobart, Tas. : 1860 - 1954)
Page 3 - DELAYS IN WORK
The floating portion of the
Hobart Bridge has been joined
in two arched lengths at the
moorings at Geilston Bay, and
is ready for thc completion of
the lift span to make it possible
to float it into position, accord-
ing to a report furnished the
Minister for Lands and Works -
The report states that construction
work was progressing favourably,
although delays at the main abut-
ment had slowed it down. The first
half of the abutment had been ex-
cavated to solid rock bottom, and
concrete carried above river level.
Work was proceeding on the second
half, and excavation was down to
an average depth of 106ft. below the
surface. Solid foundation rock
had been almost reached in the
deepest parts, although the work was
necessarily slow on account of the
great depth. It was hoped the bot-
tom would be ready for concrete
The steel frame of the uplifting
truss had been completed, and the
erection of the operating machinery
was in hand. Work on decking and
on thc machinery house was pro-
ceeding. The remainder of the steel
work for the second tower ramps
and links was almost completely
In a report on the Bridgewater
Bridge, the Minister was informed
that, because all steel workers were
required for defence works, and
the fact that certain equipment was
not obtainable, work was suspended
some months ago. At the time the
erection of the southern tower had
been completed, and two coats of
paint applied to all steel work.
Road traffic, under military con-
trol, had been able to use the new
bridge for some months, with the
northern span operated for one-way
traffic. When a few steel workers
became available shortly it was
hoped to complete the yard fabri-
cation of the north tower.
The two-plate girders which were
in temporary use as part of the
crane would be dismantled when
the north tower was completed, and
placed in position on the northern
span of the bridge. This would en-
able two-way traffic to use the whole
length of the bridge. The work
mentioned was expected to occupy
damage to tanks of oil and
spirit, which ignited. While
thc fires were being fought
thc enemy attacked with ma-
bombs were dropped on the
site. Harold William Hep-
tinstall, B.E.M., acting fire
chief, climbed on to a portion
of the damaged holder which
burning spirit tank, and dir-
ected a foam jet into the
fire. His leadership encour-
aged his men to take up posi-
tions, and eventually the fire
was extinguished. Hcptin-
stall showed courage without
regard to his own safety. It
was not until thc fires were
put out and he had seen his
men safely away that he dis-
closed he bad been injured
by the blast of an explosion.
He was appointed a member
of the Civil Division of the
Order of thc British Empire.