Hi folks,

Given the volume of jdk11u fixes I'm planning to tweak the wording of the release schedules section of the jdk-updates page to bring it in line with earlier releases.

This will involve replacing the last two paragraphs with the following text:

The first jdk-updates release in a series occurs within a month of the JDK feature GA milestone. The RDP2 date is approximately 12 weeks prior to the update release GA date.

Exceptions may be made for a limited time for urgent issues (P1s or serious regressions) at the discretion of the maintainer. If you are requesting an exception for a push post-RDP2 it should be outlined in the request justification.

JDK 11.0.2 timeline

September 2018 jdk11u forest open Late October 2018 RDP2 Mid January 2019 GA

-Rob