The duty to manage asbestos in buildings: Examples of how asbestos risks can be managed (original) (raw)

The following examples describe typical situations where asbestos could be present. They show who is responsible at each stage for acting to effectively manage asbestos risks.

The HSE publication A comprehensive guide to managing asbestos in premises has more detailed examples of individual risk assessments.

A National Health Service Trust

Background

An NHS Trust has more than 70 buildings, most of which it owns, but 15 are leased and some are rented for clinics. The Trust employs 35 maintenance workers and uses a number of building maintenance contract companies, and a preferred list of contractors.

The situation

During planned refurbishment of plant rooms, asbestos debris and overspray was discovered at the start of the site work. This was believed to have been left at the time of the original asbestos removal in the 1980s, but was not recorded on the asbestos register.

At another leased premises, a route for new network cabling was identified which avoided the asbestos-containing materials (ACMs). However, the cablers decided to use an alternative route through sprayed asbestos, resulting in several rooms becoming contaminated.

What the Trust did

To minimise the potential for any asbestos exposure in the future, the Trust recognised it needed to urgently review its asbestos management arrangements.

They also recognised the benefit of in-house asbestos expertise and set up a dedicated asbestos team and recruited a competent asbestos professional.

The team drew up an action plan which included a commitment to:

A risk-based colour coding system was also developed for plant rooms based on the type and condition of ACMs present. This informed the control arrangements for safe working of all maintenance workers.

These improvements to communicate accurate information on ACMs will help the Trust avoid repeats of the previous incidents.

Background

A local authority (LA) has approximately 35,000 properties under its control. Around 32,000 of these are domestic and the responsibility of the LA’s housing services.

Types of properties include:

The situation

Reports and records from previous asbestos surveys were kept and entered onto a corporate asbestos database.

Due to the database being used ineffectively, some properties had been surveyed more than once over the years, while others were not surveyed at all.

What the local authority did

The local authority worked with a software provider to develop a new system as their main asbestos management database which includes the asbestos register for the entire estate.

The database was designed to be compatible with the system used by the LA’s architectural and surveying service. This ensured that floor plans identifying the location of ACMs can be downloaded for maintenance workers when they are carrying out work on housing properties.

Some of the other key elements include:

The updates to the LA’s system meant specific asbestos information could be easily requested prior to commissioning works. This request is recorded on an audit trail system which ensures no request is closed down until all the required information is received. This also ensures that the system is kept up to date.

Facility management company – managing contractors undertaking unplanned or short-notice work

Background

A facility management company has around 500 properties in its nationwide portfolio. The premises range from large offices to small individual buildings, many containing ACMs.

The situation

On any day, a building may require planned or unplanned maintenance work. Although there will be many refurbishment projects, there will be far more unplanned activities, such as the replacement of light fittings, a sudden failure of an air conditioning system, or a leaking radiator.

Any one of these activities could involve the disturbance of an ACM, leading to building workers and resident staff being exposed.

What the facilities management company did

The company developed a workable and effective system to control their maintenance contractors across their premises. This involved:

An asbestos risk assessment will then be done to decide whether:

By sharing and updating existing information about ACMs, and ensuring all workers are trained correctly, the facilities management company can be sure that ACMs in their portfolio are effectively managed.

Independent school – HSE asbestos management inspection

Background

The school has 18 separate buildings, some of which were built or refurbished using asbestos in the 1960s and 1970s.

They had been using the same surveying company to annually assess the condition of identified ACMs since 2010. Each time, the school was issued with a re-inspection report and kept these reports in the bursar’s office.

The situation

One year, the usual company was unable to attend so a different surveying company was contracted. They reported ACMs that had not been previously identified.

The school was visited by HSE inspectors as part of an asbestos management inspection programme who identified a number of issues, which resulted in an Improvement Notice being served.

The issues included the following:

What the school did

To comply with the Improvement Notice, the school immediately:

They reviewed their existing asbestos management plan against HSE guidance to identify gaps in procedures and arrangements and the following:

The Improvement Notice was complied with and the school were more confident that they were effectively managing risk from their ACMs.