Blaine Road Construction Update for 9/23/2024 (original) (raw)
24-07: 2024 Southwest Area Street Reconstruction
Location
Southwest Area including:
Project Area 1
- 89th Avenue (from University Avenue to MN-65)
Project Area 2
- 87th Avenue (from dead end west of Lincoln Street to Central Avenue Service Road)
- Lincoln Street (85th Avenue to 89th Avenue)
Project Area 3
- 85th Avenue (from Lincoln Street to MN-65)
Project Area 4
- Central Avenue Service Road (From 500 feet south of 87th Avenue to the cul-de-sac just south of 89th Avenue)
Project Status as of 9/19/2024
The project consists of four phases, which can be seen on the phasing map below. Phase 1 will be completed in 2024. Phases 2A, 2B and 3 will be completed in 2025.
Phase 1
Lincoln Street/87th Avenue
Construction activities during the week of September 23 will include:
- Boulevard grading and restoration
85th Avenue
Construction activities during the week of September 23 will include:
- Boulevard grading and restoration
89th Avenue
Construction activities during the week of September 23 will include:
- Installation of concrete sidewalk
- Street grading
- Installation of the first lift of bituminous pavement
Central Avenue Frontage Road
Construction activities during the week of September 23 will include:
- Boulevard grading and restoration
Phase 2A
Construction will begin in the spring of 2025.
Phase 2B
Construction will begin in the spring of 2025.
Phase 3
Construction will begin in the spring of 2025.
If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com