Blaine Road Construction Update for 9/23/2024 (original) (raw)

24-07: 2024 Southwest Area Street Reconstruction

Location

Southwest Area including:

Project Area 1

Project Area 2

Project Area 3

Project Area 4

Project Status as of 9/19/2024

The project consists of four phases, which can be seen on the phasing map below. Phase 1 will be completed in 2024. Phases 2A, 2B and 3 will be completed in 2025.

Phase 1

Lincoln Street/87th Avenue

Construction activities during the week of September 23 will include:

85th Avenue

Construction activities during the week of September 23 will include:

89th Avenue

Construction activities during the week of September 23 will include:

Central Avenue Frontage Road

Construction activities during the week of September 23 will include:

Phase 2A

Construction will begin in the spring of 2025.

Phase 2B

Construction will begin in the spring of 2025.

Phase 3

Construction will begin in the spring of 2025.

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com