Glover Park Project » Henrico County, Virginia (original) (raw)

Project Status: In Progress

Estimated Cost: $40 million
Start Date: July 2019
Estimated End Date: 2026

11217 Greenwood Road
Glen Allen, VA 23059

Magisterial District: Brookland

This project will continue development for community recreation amenities and a tournament-level sports complex at Glover Park. Phase I of the park included a master plan of development for the original 90 acres of park land. Henrico County has acquired over 100 acres of park property, through purchase and donation, since the master plan was first adopted and now totals 209 acres. The Phase II Amended Master Plan was adopted by the Board of Supervisors in fall 2022.

Project Description

Community amenities will include:

Park amenities will open as they are completed. The dog park, playground, multi-purpose fields, and trails will open in late spring 2026. Baseball amenities, including the private development, will open late 2026 in time for the 2027 spring season.

Progress to Date

June 2024: Construction began.

February 2024: Trees cleared for construction.

January 2024: The Board voted to award a 30.3millionforconstructionofPhaseIIatGloverParktoSouthwoodBuildingSystemInc.30.3 million for construction of Phase II at Glover Park to Southwood Building System Inc. 30.3millionforconstructionofPhaseIIatGloverParktoSouthwoodBuildingSystemInc.18.1 million was added to the project budget with this award of contract.

2016: Bond Referendum passed by Henrico voters allocating $20 million for this project.