Investigating the Factors That Cause Cost and Time Overrun in the Residential Construction Projects in the Uae: Project Managers Perspective (original) (raw)
Abstract
The construction industry is considered an essential element to stabilize countries economically. In the UAE, this sector has received a lot of attention and development since the discovery of oil. This has enhanced the continuous expansion in construction activities. Recently, the construction projects in the UAE and KSA together reached 60% of the whole projects in the Middle East region, and the majority of it was in Dubai, which in 2018 enhanced its Gross Domestic Product (GDP) to reach 14.5%. Therefore, the decision-makers apply multiple methods at different projects in order to achieve the prime factors for project success which are: cost, time, quality, and safety. However, there are different variables and unpredictable causes that are faced by the construction industry, such as the availability of the main resources, different environmental conditions, financial issues, political conditions, poor productivity, and contractual relations. Meanwhile, there is a great interest ...
Loading Preview
Sorry, preview is currently unavailable. You can download the paper by clicking the button above.
References (116)
- Abdel-Wahab, M. S., Dainty, A. R. J., Ison, S. G., Bowen, P., & Hazlehurst, G. (2008). Trends of skills and productivity in the UK construction industry. Engineering, Construction and Architectural Management, 15(4), 372-382. https://doi.org/10.1108/09699980810886865
- Abdul-Rahman, H., Berawi, M. A., Berawi, A. R., Mohamed, O., Othman, M., & Yahya, I. A. (2006). Delay Mitigation in the Malaysian Construction Industry. Journal of Construction Engineering and Management, 132(2), 125-133. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:2(125)
- Abdul-Rahman, Takim, R., & Min, W. S. (2009). Financial-related causes contributing to project delays. Journal of Retail & Leisure Property, 8(3), 225-238. https://doi.org/10.1057/rlp.2009.11
- Acharya, N. K., Dai Lee, Y., & Man Im, H. (2006). Conflicting factors in construction projects: Korean perspective. Engineering, Construction and Architectural Management, 13(6), 543-566. https://doi.org/10.1108/09699980610712364
- Adafin, J., Rotimi, J. O. B., & Wilkinson, S. (2020). Risk impact assessments in project budget development: Quantity surveyors' perspectives. International Journal of Construction Management, 20(1), 13-28. https://doi.org/10.1080/15623599.2018.1462441
- Adam, A., Josephson, P.-E. B., & Lindahl, G. (2017). Aggregation of factors causing cost overruns and time delays in large public construction projects: Trends and implications. Engineering, Construction and Architectural Management, 24(3), 393-406. https://doi.org/10.1108/ECAM-09-2015-0135
- Ahmed et al. (2003). Delays in Construction: A Brief Study of the Florida Construction Industry. Retrieved February 12, 2019, from http://ascpro0.ascweb.org/archives/cd/2003/2003pro/2003/Ahmed03.htm
- Ahzahar, N., Karim, N. A., Hassan, S. H., & Eman, J. (2011). A Study of Contribution Factors to Building Failures and Defects in Construction Industry. Procedia Engineering, 20, 249-255. https://doi.org/10.1016/j.proeng.2011.11.162
- Aimable, S. (2016). The causative factors leading to cost overrun in dam construction projects in rwanda: case study kinoni 1 dam construction project. https://www.academia.edu/22214619/the\_causative\_factors\_leading\_to\_cost\_ overrun_in_dam_construction_projects_in_rwanda_case_study_kinoni_1_da m_construction_project
- Akanni, P. O., Oke, A. E., & Akpomiemie, O. A. (2015). Impact of environmental factors on building project performance in Delta State, Nigeria. HBRC Journal, 11(1), 91-97. https://doi.org/10.1016/j.hbrcj.2014.02.010
- Akintoye, A. (2000). Analysis of factors influencing project cost estimating practice. Construction Management and Economics, 18(1), 77-89. https://doi.org/10.1080/014461900370979
- Akintoye, A., & Fitzgerald, E. (2000). A survey of current cost estimating practices in the UK. Construction Management and Economics, 18(2), 161-172. https://doi.org/10.1080/014461900370799
- Al Jurf, N., & Beheiry, S. (2012). Factors affecting cost and schedule in Qatar's residential compounds projects. International Journal of Engineering Management and Economics, 3(1-2), 117-134. https://doi.org/10.1504/IJEME.2012.048608
- Alaghbari, W., Razali A. Kadir, Mohd., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206. https://doi.org/10.1108/09699980710731308
- Alaryan, A., Elshahat, A., & Dawood, M. (2014). Causes and Effects of Change Orders on Construction Projects in Kuwait, 4(7), 1-8.
- Albattah, M., Saheed, A., & Shafiq, M. (2019). Employment of unskilled craft workers in the UAE construction projects: Explicating the reasons. 8, 410- 414. https://doi.org/10.35940/ijitee.J1076.08810S19
- Alghonamy, A. (2015). Cost Overrun in Construction Projects in Saudi Arabia: Contractors' Perspective. International Journal of Engineering, 15(04), 35- 42.
- Alhajeri, M. (2011) Health and Safety in the Construction Industry: Challenges and Solutions in the UAE. Doctoral Dissertation. Coventry: Coventry University, United Kingdom.
- Al-Hammad, A., & Assaf, S. (1992). Design-Construction interface problems in Saudi Arabia. Building Research & Information, 20(1), 60-63. https://doi.org/10.1080/09613219208727172
- Aljassmi, H. A., & Han, S. (2014). Classification and occurrence of defective acts in residential construction projects. Journal of Civil Engineering and Management, 20(2), 175-185. https://doi.org/10.3846/13923730.2013.801885
- Al-Khaldi. (1990). Factors affecting the accuracy of construction costs estimating in Saudi Arabia-KFUPM ePrints. Retrieved May 5, 2020, from https://eprints.kfupm.edu.sa/id/eprint/10083/
- Al-Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3-23. https://doi.org/10.1080/01446190802541457
- Alzebdeh, K., Bashir, H. A., & Siyabi, S. K. A. (2015). Applying Interpretive Structural Modeling to Cost Overruns in Construction Projects in the Sultanate of Oman. The Journal of Engineering Research [TJER], 12(1), 53- 68. https://doi.org/10.24200/tjer.vol12iss1pp53-68
- Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015a). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1), 198-214. https://doi.org/10.1108/IJMPB-04-2014-0035
- Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015b). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1), 198-214. https://doi.org/10.1108/IJMPB-04-2014-0035
- Arab World Competitiveness Report 2007. (2007). Belfer Center for Science and International Affairs. https://www.belfercenter.org/node/89514
- Arslan, G., Tuncan, M., Birgonul, M. T., & Dikmen, I. (2006). E-bidding proposal preparation system for construction projects. Building and Environment, 41(10), 1406-1413. https://doi.org/10.1016/j.buildenv.2005.05.024
- Asif, M. (2016a). Growth and sustainability trends in the buildings sector in the GCC region with particular reference to the KSA and UAE. Renewable and Sustainable Energy Reviews, 55, 1267-1273. https://doi.org/10.1016/j.rser.2015.05.042
- Asif, M. (2016b). Growth and sustainability trends in the buildings sector in the GCC region with particular reference to the KSA and UAE. Renewable and Sustainable Energy Reviews, 55, 1267-1273. https://doi.org/10.1016/j.rser.2015.05.042
- Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of Delay in Large Building Construction Projects. Journal of Management in Engineering, 11(2), 45-50. https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)
- Bal, M., Bryde, D., Fearon, D., & Ochieng, E. (2013). Stakeholder Engagement: Achieving Sustainability in the Construction Sector. Sustainability, 5(2), 695-710. https://doi.org/10.3390/su5020695
- Bentil, E., nana-addy, E., Asare, E., & Fokuo-Kusi, A. (2017). The Level of Existence and Impact of Cost and Time Overruns of Building Construction Projects in Ghana. Journal of Civil and Environmental Research, 9, 36-44.
- Blismas, N. G., Sher, W. D., Thorpe, A., & Baldwin, A. N. (2004). Factors influencing project delivery within construction clients' multi-project environments. Engineering, Construction and Architectural Management, 11(2), 113-125. https://doi.org/10.1108/09699980410527858
- Boyatzis, R. E. (1998). Transforming Qualitative Information: Thematic Analysis and Code Development. SAGE.
- Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77-101. https://doi.org/10.1191/1478088706qp063oa
- Cassell, C., & Symon, G. (2004). Essential Guide to Qualitative Methods in Organizational Research. SAGE.
- Challal, A., & Tkiouat, M. (2012). Qualitative Approach Risk Period in Construction Projects. Journal of Financial Risk Management, 1(3), 42-51. https://doi.org/10.4236/jfrm.2012.13008
- Chan, A. P. C., Scott, D., & Chan, A. P. L. (2004). Factors Affecting the Success of a Construction Project. Journal of Construction Engineering and Management, 130(1), 153-155. https://doi.org/10.1061/(ASCE)0733- 9364(2004)130:1(153)
- Couzens, A., Skitmore, M., Thorpe, T., & Mcaffer, R. (1996). Strategic information requirements in contract bidding: framework for development of a decision support system. Civil Engineering Systems, 13(2), 121-139. https://doi.org/10.1080/02630259608970191
- Cox, A., & Townsend, M. (1997). Latham as half-way house: A relational competence approach to better practice in construction procurement. Engineering Construction and Architectural Management, 4(2), 143-158. https://doi.org/10.1046/j.1365-232X.1997.00085.x
- Creswell, J. W. (2014). The selection of a research approach. Research Design: Qualitative, Quantitative, and Mixed Methods Approaches, 12, 3-24.
- Dai, J., Goodrum, P. M., & Maloney, W. F. (2007). Analysis of craft workers' and foremen's perceptions of the factors affecting construction labour productivity. Construction Management and Economics, 25(11), 1139-1152. https://doi.org/10.1080/01446190701598681
- El Alaghbari, A Salim, M R Abdul Kadir, & A Asonway. (2008). Factors affecting speed of industrialized building system (ibs) projects in malaysia. https://doi.org/10.13140/2.1.3380.6089
- Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners' Perspective of Factors Contributing to Project Delay: Case Studies of Road and Bridge Projects in Saudi Arabia. Procedia Engineering, 145, 1402-1409. https://doi.org/10.1016/j.proeng.2016.04.176
- El-Karim, M. S. B. A. A., Nawawy, O. A. M. E., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC Journal, 13(2), 202-216. https://doi.org/10.1016/j.hbrcj.2015.05.001
- El-Sayegh, S. M. (2008). Risk assessment and allocation in the UAE construction industry. International Journal of Project Management, 26(4), 431-438. https://doi.org/10.1016/j.ijproman.2007.07.004
- Emam, H., Farrell, P., & Abdelaal, M. (2015, September). Causes of delay on infrastructure projects in Qatar. In Proceedings of the 31st Annual ARCOM Conference, Lincoln, UK, Association of Researchers in Construction Management, Nottingham, UK (pp. 773-782).
- Enshassi, A., Mohamed, S., & Abushaban, S. (2009). Factors affecting the performance of construction projects in the gaza strip. Journal of civil engineering and management, 15(3), 269-280. https://doi.org/10.3846/1392- 3730.2009.15.269-280
- Fanouse, R. (2017). An Exploration of the Causes of Cost Overruns in Public Sector Infrastructure Projects in the United Arab Emirates (UAE): A Stakeholder Perspective, Doctoral Dissertation, The British University in Dubai.
- Faridi, A. S., & El-Sayegh, S. M. (2006a). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176. https://doi.org/10.1080/01446190600827033
- Faridi, A. S., & El-Sayegh, S. M. (2006b). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176. https://doi.org/10.1080/01446190600827033
- Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of Project Management, 21(5), 321-326. https://doi.org/10.1016/S0263-7863(02)00055-8
- Ghaljaie, F., Naderifar, M., & Goli, H. (2017). Snowball Sampling: A Purposeful Method of Sampling in Qualitative Research. Strides in Development of Medical Education, 14(3). https://doi.org/10.5812/sdme.67670
- Ghazal, M. M., & Hammad, A. (2020). Application of knowledge discovery in database (KDD) techniques in cost overrun of construction projects. International Journal of Construction Management, 9(10), 1-15. https://doi.org/10.1080/15623599.2020.1738205
- Gill et al. (2008). Methods of data collection in qualitative research: Interviews and focus groups | British Dental Journal. Retrieved July 23, 2019, from https://www.nature.com/articles/bdj.2008.192?fbclid=IwAR3dnG9E1kiF- kBEfvXjf1cvcxu-
- Han, S. H., & Diekmann, J. E. (2001). Making a risk-based bid decision for overseas construction projects. Construction Management and Economics, 19(8), 765- 776. https://doi.org/10.1080/01446190110072860
- Harris, P. F., & McCaffer, P. R. (2013). Modern Construction Management. John Wiley & Sons.
- Hasani, M. A. (2018). Cultural and Economic Risks Factors in UAE Construction Projects. International Journal of Academic Research in Business and Social Sciences, 8(12), Pages 449-471. https://doi.org/10.6007/IJARBSS/v8- i12/5044
- Horton, J., Macve, R., & Struyven, G. (2004). Qualitative Research: Experiences in Using Semi-Structured Interviews. In The Real Life Guide to Accounting Research (pp. 339-357). Elsevier. https://doi.org/10.1016/B978-008043972- 3/50022-0
- Hosani, I. I. A., Dweiri, F. T., & Ojiako, U. (2020). A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates. International Journal of System Assurance Engineering and Management, 11(6), 1-10.
- Hsieh, T., Lu, S., & Wu, C. (2004). Statistical analysis of causes for change orders in metropolitan public works. International Journal of Project Management, 22(8), 679-686. https://doi.org/10.1016/j.ijproman.2004.03.005
- Iyer, K. C., & Jha, K. N. (2005). Factors affecting cost performance: Evidence from Indian construction projects. International Journal of Project Management, 23(4), 283-295. https://doi.org/10.1016/j.ijproman.2004.10.003
- Johnson, R. M., & Babu, R. I. I. (2020). Time and cost overruns in the UAE construction industry: A critical analysis. International Journal of Construction Management, 20(5), 402-411. https://doi.org/10.1080/15623599.2018.1484864
- Joshi, A., Kale, S., Chandel, S., & Pal, D. K. (2015). Likert Scale: Explored and Explained. Current Journal of Applied Science and Technology, 396-403. https://doi.org/10.9734/BJAST/2015/14975
- Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management & Economics, 15(1), 83-94. https://doi.org/10.1080/014461997373132
- Kazaz, A., & Ulubeyli, S. (2004). A different approach to construction labour in Turkey: Comparative productivity analysis. Building and Environment, 39(1), 93-100. https://doi.org/10.1016/j.buildenv.2003.08.004
- Kog, Y. C., Chua, D. K. H., Loh, P. K., & Jaselskis, E. J. (1999). Key determinants for construction schedule performance. International Journal of Project Management, 17(6), 351-359. https://doi.org/10.1016/S0263-7863(98)00058- 1
- Koushki, P. A. K. C., Al-Rashid, K., & Kartam, N. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), 285-294. https://doi.org/10.1080/0144619042000326710
- Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), 04015032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391
- Laufer, A., Howell, G. A., & Rosenfeld, Y. (1992). Three modes of short-term construction planning. Construction Management and Economics, 10(3), 249-262. https://doi.org/10.1080/01446199200000021
- Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(6), 367-377. https://doi.org/10.1007/s12205-008-0367-7
- Lim, E. H., & Ling, F. Y. Y. (2002). Model for predicting clients' contribution to project success. Engineering Construction and Architectural Management, 9(5-6), 388-395. https://doi.org/10.1046/j.1365-232X.2002.00268.x
- Love, P. E. D., Wang, X., Sing, C., & Tiong, R. L. K. (2013). Determining the Probability of Project Cost Overruns. Journal of Construction Engineering and Management, 139(3), 321-330. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000575
- Mahamid, I. (2015). Factors affecting cost estimate accuracy: Evidence from Palestinian construction projects. International Journal of Management Science and Engineering Management, 10(2), 117-125. https://doi.org/10.1080/17509653.2014.925843
- Mahamid, I. (2016). Micro and macro level of dispute causes in residential building projects: Studies of Saudi Arabia. Journal of King Saud University - Engineering Sciences, 28(1), 12-20. https://doi.org/10.1016/j.jksues.2014.03.002
- Mahamid, I., & Dmaidi, N. (2013). Risks leading to cost overrun in building construction from consultants' perspective. Organization, technology & Management in Construction: An International Journal, 5(2), 860-873.
- Manley, K. (2008). Against the odds: Small firms in Australia successfully introducing new technology on construction projects. Research Policy, 37(10), 1751-1764. https://doi.org/10.1016/j.respol.2008.07.013
- Mehran, D. (2016). Exploring the Adoption of BIM in the UAE Construction Industry for AEC Firms. Procedia Engineering, 145, 1110-1118. https://doi.org/10.1016/j.proeng.2016.04.144
- Minato, T. (2003). Representing causal mechanism of defective designs: A system approach considering human errors. Construction Management and Economics, 21(3), 297-305. https://doi.org/10.1080/0144619032000056135
- Mohamed & Salwa. (2016). The applicability of just-in-time in United Arab Emirates construction projects. Journal of Emerging Trends in Engineering and Applied Sciences, 7(2), 120-128. https://doi.org/10.10520/EJC190069
- Motaleb, O. H. (2014). Development of a risk response model to handle delays of construction projects in the United Arab Emirates (Doctoral dissertation), 431. Motaleb, O., & Kishk, M. (2010, September). An investigation into causes and effects of construction delays in UAE. In Procs 26th Annual ARCOM Conference (pp. 6-8).
- Mpofu, B., Ochieng, E. G., Moobela, C., & Pretorius, A. (2017). Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management, 24(2), 346-376. https://doi.org/10.1108/ECAM-05-2015-0072
- Noushad, S., Naseem, A., & Ameer Ali, N. (2006). A "Construction Industry Payment And Adjudication Act": Reducing Payment-Default And Increasing Dispute Resolution Efficiency In Construction. In International Forum Construction Industry Payment Act and Adjudication (Vol. 13).
- Nowell, L. S., Norris, J. M., White, D. E., & Moules, N. J. (2017). Thematic Analysis: Striving to Meet the Trustworthiness Criteria. International Journal of Qualitative Methods, 16(1), 1609406917733847. https://doi.org/10.1177/1609406917733847
- Okpala, D. C., & Aniekwu, A. N. (1988). Causes of High Costs of Construction in Nigeria. Journal of Construction Engineering and Management, 114(2), 233- 244. https://doi.org/10.1061/(ASCE)0733-9364(1988)114:2(233)
- Oyedele, L. O., & Tham, K. W. (2007). Clients' assessment of architects' performance in building delivery process: Evidence from Nigeria. Building and Environment, 42(5), 2090-2099. https://doi.org/10.1016/j.buildenv.2005.06.030
- Patil, Y. K., & Bhangale, P. P. (2016). Investigation of Factors Influencing Cost Overrun in High Rise Building Construction. International Journal of Latest Trends in Engineering and Technology (IJLTET), 6, 338.
- Phaobunjong, K. (2002). Parametric cost estimating model for conceptual cost estimating of building construction projects [Thesis]. Retrieved September 14, 2020, from https://repositories.lib.utexas.edu/handle/2152/845
- Phua, F. T. T. P. C. (2005). Determining the relationship between fee structure and project performance between firms: An empirical study based on institutional and task environment perspectives. Construction Management and Economics, 23(1), 45-56. https://doi.org/10.1080/0144619042000287796
- Potts, K., & Ankrah, N. (2014). Construction Cost Management: Learning from Case Studies. Routledge.
- Proverbs, D. G., & Holt, G. D. (2000). A theoretical model for optimum project (time) performance based on European best practice. Construction Management and Economics, 18(6), 657-665. https://doi.org/10.1080/014461900414718
- Rahman, I. A., Hameed Mem, A., & Abd. Karim, A. T. (2013). Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia. Journal of Applied Sciences, 13(2), 286-293. https://doi.org/10.3923/jas.2013.286.293
- Ren, Z., Atout, M., & Jones, J. (2008, September). Root causes of construction project delays in Dubai. In Procs 24th Annual ARCOM Conference (pp. 1-3).
- Richie, D. A., & Ross, J. A. (2016). Advances in Run-time Performance and Interoperability for the Adapteva Epiphany Coprocessor. Procedia Computer Science, 80, 1531-1541. https://doi.org/10.1016/j.procs.2016.05.478
- Ruqaishi, M., & Bashir, H. A. (2015). Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf Cooperation Council Countries: A Case Study. Journal of Management in Engineering, 31(3), 05014017. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000248
- Russell, A. D., & Udaipurwala, A. (2000). Assessing the Quality of a Construction Schedule. Construction Congress VI, 928-937. https://doi.org/10.1061/40475(278)97
- Salama, M., & Habib, A. P. (2009, September). Investigating the causes of variation within the construction projects in UAE. In Procs 25th Annual ARCOM Conference (pp. 7-9).
- Samarghandi, H., Mousavi, S., Taabayan, P., Mir Hashemi, A., & Willoughby, K. (2016). Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran. Retrieved June 27, 2020, from https://harvest.usask.ca/handle/10388/11493
- Sambasivan, M., & Soon, Y. W. (2007a). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007
- Sambasivan, M., & Soon, Y. W. (2007b). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007
- Sharma, S., & Goyal, P. K. (2014). Cost overrun factors and project cost risk assessment in construction industry-a state of the art review. International Journal of Civil Engineering (IJCE), 3, 139-154.
- Shebob, A., Dawood, N., Shah, R. K., & Xu, Q. (2012). Comparative study of delay factors in Libyan and the UK construction industry. Engineering, Construction and Architectural Management, 19(6), 688-712. https://doi.org/10.1108/09699981211277577
- Shibnai, A., & Salah, K. (2015). Time and cost overrun in construction projects in Egypt. Retrieved June 20, 2020, from URL https://www. researchgate. net/profile/Dr_Abdussalam_Shibani/publication.
- Smith, A. J. (2017). Estimating, Tendering and Bidding for Construction Work. Macmillan International Higher Education.
- Stewart, R. D. (1991). Cost Estimating. John Wiley & Sons.
- Subramani, T. (2014). Causes of Cost Overrun In Construction. IOSR Journal of Engineering, 4(6), 01-07. https://doi.org/10.9790/3021-04640107
- Sweis, G. J. (2013). Factors Affecting Time Overruns in Public Construction Projects: The Case of Jordan. International Journal of Business and Management, 8(23), 120. https://doi.org/10.5539/ijbm.v8n23p120
- Sweis, Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665-674. https://doi.org/10.1016/j.ijproman.2007.09.009
- Tahir, M. M., & Baba, D. L. (2018). Improving Cost and Time Control in Construction Using Building Information Model (BIM): A Review. Pertanika Journal of Science and Technology, 26 (1): 21 -36
- Toh, T.-C., Ting, C., Ali, K.-N., Aliagha, G.-U., & Munir, O. (2012). Critical Cost Factors of Building Construction Projects in Malaysia. Procedia -Social and Behavioral Sciences, 57, 360-367. https://doi.org/10.1016/j.sbspro.2012.09.1198
- Tsang, K. K. (2012). The use of midpoint on Likert Scale: The implications for educational research. Hong Kong Teachers' Centre Journal, 11(1), 121-130.
- Tukey, J. W. (1962). The Future of Data Analysis. The Annals of Mathematical Statistics, 33(1), 1-67.
- Waziri. (2016). Design and Construction Defects Influencing Residential Building Maintenance in Nigeria. Jordan Journal of Civil Engineering, 10(3), 313- 323. https://doi.org/10.14525/JJCE.10.3.3605
- Yusof, N., & Iranmanesh, M. (2017). The Impacts of Environmental Practice Characteristics on Its Implementation in Construction Project. Procedia Environmental Sciences, 37, 549-555. https://doi.org/10.1016/j.proenv.2017.03.040
- Zaghloul, R., & Hartman, F. (2003). Construction contracts: The cost of mistrust. International Journal of Project Management, 21(6), 419-424. https://doi.org/10.1016/S0263-7863(02)00082-0
- Zhao, L., Mbachu, J., & Liu, Z. (2020, April 30). Identifying Significant Cost- Influencing Factors for Sustainable Development in Construction Industry Using Structural Equation Modelling [Research Article]. Mathematical Problems in Engineering. https://doi.org/10.1155/2020/4810136