Analysis Of Scheduling Acceleration Of Worship Building Construction In Dili Timor-Leste Using Time Cost Trade Off (TCTO) Method (original) (raw)
Planning is the most significant part to achieve success of construction project. The planning itself towards construction project has an impact on revenue in the project itself. Frequently, a project must be completed sooner than its normal time. In this case, the project leader is expected to issue how to accelerate the completion of the project with a minimum cost. The objectives that are expected to achieve from this research are: 1) analyzing the normal time scheduling?, 2) analyzing the scheduling acceleration of the development 3) analyzing changes in the cost increase in development. From the acceleration with time cost trade off (TCTO) method on a worship building project in Dili Timor-Leste, it is optimum to be able to reduce the time duration by adding resources/working groups, and having project cost increase. In the worship building construction project in Dili Timor-Leste, the initial duration of the project is 223 days and it is changed to 181 days, so that there are ...