Sprint and its importance in Agile Scrum (original) (raw)

Last Updated : 2 Jun, 2026

Sprint is a fixed-length iteration and an agile scrum event, during which a cross-functional scrum team works to complete a set amount of work. Generally, a sprint is time-boxed to a 2 to 4-week duration. Sprint breaks down complex tasks in product or project development into shorter durations with a well-defined sprint goal, and it results in a potentially shippable Product Increment (PI).

**Purpose of Sprint

The purpose of a Sprint is defined as a product increment or to make specific and planned progress against the product goal. Each Sprint purpose or goal is determined during the Sprint planning meeting and agreed upon by the Scrum Team, which includes the Product Manager, Development Team, and Scrum Master.

**Definition of Agile

Agile is a flexible, adaptive, and collaborative project development approach that breaks down projects into short iterations called Sprints of 2 to 4 weeks. Agile has 4 values and 12 principles called the Agile Manifesto. Agile frameworks include Scrum, Kanban, Extreme Programming (XP), Disciplined Agile (DA), Large Scale Scrum (LeSS) and Scaled Agile Framework (SAFe)

**Sprint in Agile

product_assigned_features_to_sprint

In Agile, a Sprint is a time-boxed iteration of 2 to 4 weeks, during which the scrum team works to complete a set amount of work planned during sprint planning meetings. Sprint is a fundamental component of Scrum, which is one of the popular Agile frameworks.

**Sprints in Agile Scrum

They are used by the entire Scrum team which includes the Development Team, Scrum Master and Product Owner.

Characteristics of a Sprint

The key characteristics of a Sprint are listed below.

  1. **Time-Boxed Duration: A sprint has a fixed, time-boxed duration which is determined by the Scrum Team based on the team's capacity and the nature of the project. As a general practice, this duration is consistent throughout a project for predictability.
  2. **Fixed Sprint Goal: Each Sprint has a well-defined, clear and concise Sprint goal with planned objectives the team aims to achieve.
  3. **Iterative Process: Sprints are continuous and repetitive with each sprint working on top of what was achieved in the previous sprint.
  4. **Incremental Development: From each sprint the product is built incrementally, and releases done to product increments.
  5. **Collaborative Teamwork: Sprints are executed by the Collaborative efforts of all team members including the product owner, scrum master and development team. They work together to plan, execute and review the sprint.
  6. **Adaptive: Sprint is adaptive and flexible to adjust the scope of the sprint based on customer feedback and markets' changing requirements.
  7. **Potentially Shippable Product Increment: The primary objective of each sprint is to deliver a well-defined potentially shippable product increment that meets the 'definition of done.
  8. **Empirical Process Control: Based on the feedback, data and experience of Sprint Review and Sprint Retrospective events, the empirical process is implemented. Empirical process control helps the team to continuously inspect and adapt their work for improvement.
  9. **Stakeholder Engagement: Sprints engages all stakeholders during the sprint cycle, to engage and receive feedback which promotes transparency and alignment with stakeholders' needs.

Purpose of Sprint in Agile Scrum

Below is the list of items that serve the purpose of a Sprint:

The outcome of a Sprint

The outcome of a Sprint is measured by the tangible and demonstrable product increment, based on the sprint goal and sprint backlog. Below are the key outcomes of a Sprint:

The Sprint Lifecycle

sprint_cycle

The Sprint Lifecycle in Agile Scrum is a repetitive, time-boxed cycle used for developing and managing software products. It operates on the core Scrum pillars of transparency, inspection, and adaptation, enabling continuous improvement.

Each Sprint is a fixed-duration iteration, typically lasting between one to four weeks, with a clear start and end date. As soon as one Sprint ends with its deliverables, the next Sprint begins immediately. This iterative approach allows teams to deliver working increments of the product frequently and respond flexibly to changes.

The Sprint Lifecycle consists of five key events:

Working of Sprint In an Agile Framework

Sprint in agile is characterized by many events and activities. Below are the key items based on how Sprint works in an agile framework:

Benefits of working in sprints

Essentials to running a successful sprint

Following are the elements and best practices to ensure a successful Sprint in agile scrum:

Steps to Create and Run a Sprint

Creating a Sprint involves a set of well-defined steps and processes. Below is the step-by-step guide to creating a sprint:

  1. A ready-to-work product backlog list of features and functions for the specific product is the first step before creating a sprint.
  2. Schedule the Sprint with duration and begin and end dates.
  3. Sprint Planning meeting is held before the Sprint begins.
  4. Sprint execution with daily standup meetings to monitor progress.
  5. Update the status of work completed and in progress.
  6. Progress is monitored using a burndown chart.
  7. Sprint review is done after the completion of all backlog items planned for the sprint.
  8. Verify the Definition of Done.
  9. Hold the Sprint retrospective meeting.
  10. End of the current sprint and begin the next sprint.

Jira Example for creating a Sprint:

Jira is a project/product management tool used by teams to add and track the progress of project/product issues, user stories and releases. We will explore the Sprint actions from Jira software.

Below are steps to create a New Sprint, start a Sprint and Complete a Sprint:

**Step 1: To begin log in to the Jira tool.

LoginToJira

**Step 2: Select your project from the list of projects available.

SelectProject

In this demo, I'm selecting the project 'Project2023'.

**Step 3: View product backlog items created in the project selected above.

SprintBacklog

**Step 4: Edit Backlog Item. After creating a backlog item or adding it to a sprint, it can be edited by selecting the particular item. A window will appear to the right of the item selected. You can add or update a description and add or edit other information like assignee, Sprint name, Story point estimated value and the fix version number for issue.

EditBacklogItem

Create New Sprint

Below are the steps for creating a new Sprint from Jira.

**Step 1: Create the New Sprint

CreateNewSprint2

Click the 'Create Sprint' button on atop right of a backlog items list to create a new Sprint.

**Step 2: Add a New Issue to the New Sprint

Once a planned Sprint is created, we can add new tasks or issues can be added to the new Sprint created.

CreateNewIssueForNewSprint

Click the 'Create Issue' button and an editable area appear above the button to add details of the issue.

**Step 3: Drag an Item to the New Sprint from the backlog items. You can add as many items as required and plan for a specific Sprint.

DragItemToNewSprint

**Step 4: Edit Sprint Dates and add Sprint goal.

Select Add date or click of the 3 dots at the top right end of a sprint and a popup menu displays, select 'Edit the sprint' menu to add or edit dates.

EditSprintDates

Start a New Sprint

**Step 1: Start a Sprint

After all backlog items are added to a particular Sprint and ready, you can click the 'Start Sprint' button to begin a new Sprint.
StartSprint

**Step 2: View Sprint Progress

As Sprint progresses and the scrum team works on the issues and tasks from the Sprint, the progress and status of the Sprint items can be viewed from the 'Timeline' tab at the left of the selected project.

ViewSprintProgress

**Step 3: Sprint task status

When we need to change the status of a task or issue, it can be changed by selecting the item from the list of items in the Sprint and changing the status to 'In Progress' and 'Done' The 'To Do' status is the default when we create a new task or issue.
ChangeStatus

Step 4: Complete a Sprint

When a Sprint is completed after the specified time and 'Definition of Done' is accepted by all team members after Sprint Review, the 'Sprint' can be set to be completed by clicking the 'Complete Sprint' button.

CompleteSprint

After the 'Complete Sprint' button is clicked below confirmation window appears. Select the helps 'Complete Sprint' button.

CompleteSprint2